CITY STREET/SIDEWALK PROJECTS
|
| Little Texas Road Sidewalk |
The City of Kannapolis and North Carolina Department of Transportation held a public meeting regarding the construction of a sidewalk on Little Texas Road on January 26, 2021.
The Little Texas Sidewalk Project includes approximately one and half miles of sidewalk and pedestrian improvements along the east side of Little Texas Road and Ruth Avenue from Dale Earnhardt Boulevard to Lane Street. The project also includes improvements to the intersection of Ruth Avenue and Little Texas Road and roadway improvements along Ruth Avenue.
These improvement are designed to assist people to more easily walk or bike to the surrounding neighborhoods, businesses and school in this area. Construction of the project is expected to begin in 2026.
If you missed the meeting you are welcome to watch it at this link - Little Texas Sidewalk Public Meeting - YouTube
Project Map 1
Project Map 2
Project Map 3
|
Acquisition of Right-Of-Way Begins Summer 2023
Construction Begins 2026
|
16 to18 months after construction begins
|
| Bethpage Road Sidewalk |
Construct 7-foot sidewalk, curb and gutter, and associated storm drainage along the south side of Bethpage Road from South Main Street to existing sidewalk at Leonard Avenue and along the south side of Bethpage Road from Westgreen Drive to Klondale Avenue |
Design underway Summer 2023
Acquisition of Right-Of-Way
2026
Construction Begins TBD
|
TBD |
| Construction of North Main Street Sidewalk |
Construction of sidewalk |
2025 |
TBD |
| |
|
|
|
DOWNTOWN REVITALIZATION PROJECT
|
| |
The initial phases of the Downtown Revitalization Project are completed. Additional phases include development of remaining properties downtown including Harris Teeter, homes and apartments. |
|
|
| |
|
|
|
NCDOT
|
| NCDOT Projects |
Updated Information on all NCDOT Projects is located at www.ncdot.gov. Below is an update on NCDOT projects in Kannapolis. |
|
|
| Kannapolis Train Station Improvements |
Construction of a new passenger rail platform, pedestrian overpass and new parking adjacent to the station. |
2022 |
TBD |
| East First Street Bridge |
Replacement of the bridge on East First Street over U.S. 29 |
2022 |
2026 |
| Lake Fisher Bridge |
Replacement of the bridge on Brantley Road. |
TBD |
TBD |
| U.S. 29/601 |
Conversion of the existing interchange to a diverging diamond. |
TBD |
TBD |
| NC 3 and US 29/601 Intersection |
Install U-turn bulbs on Cannon Blvd to remove left turns at the intersection of NC 3 and US 29/Cannon Boulevard. Includes sidewalk and mast arm utility poles. Improvement to storm drainage through Eastwood neighborhood |
TBD |
TBD |
| NC Rail North Kannapolis Railroad Crossing Work |
Construction of separated grade rail crossing at Rogers Lake Road at Main Street and Ridge Avenue. Work is underway. |
2022 |
TBD |
| N.C. 73 Improvements (Mecklenburg & Cabarrus) |
Planning and design are underway to widen a 14-mile stretch of N.C. 73 from two to four lanes between N.C. 115 (Old Statesville Road) and U.S. 29 (Concord Parkway North) in Mecklenburg and Cabarrus counties. |
2023 |
Click here |
| Rogers Lake Rd Grade Separation |
Work is underway. |
2023 |
24-36 months after construction begins |
PARKS & RECREATION
|
| Irish-Buffalo Creek Greenway |
Phase One (Construction) This is a 2.7 mile; 10 foot wide paved greenway trail which will connect Orphanage Rd. to Rogers Lake Rd. There is also a connection over to Oakwood Ave. Phase Two planning is underway. |
Fall 2019 |
Completed and Opened in 2021 |
| Rocky River Greenway |
One mile extension of the current greenway. It is a 10ft. wide paved greenway trail which will run along the Rocky River from the Mecklenburg County line to the NC 73 bridge. |
TBD |
TBD |
| Westside Park/Eastside Park |
New parks on the west and east side of the City. Design is underway for Eastside Park. |
2025 |
TBD |
PLANNING
|
| Cannon Boulevard Corridor Plan |
The Cannon Boulevard Corridor Plan (CBCP) is a land use and transportation plan which will guide future redevelopment of Cannon Boulevard. The CBCP is intended to provide a long-range vision for the transformation of Cannon Boulevard into a 21st century thoroughfare. The plan will include strategic land use, transportation and design recommendations to facilitate this transformation. Cannon Boulevard (US 29) is a major transportation and commercial corridor which serves the City of Kannapolis, along with surrounding communities and the greater Cabarrus County/Rowan County area. Implementation isTBD. |
Fall 2019 |
2021 |
| |
|
|
|
WATER & SEWER
|
| Royal Oaks Rehab |
Replace and rehabilitate existing water and sanitary sewer lines. Project delayed due to lack of funds. |
TBD |
TBD |
| Summit Ridge Sewer |
Replacement of an existing portion of sanitary sewer pipe along Chambers Branch on Summit Ridge Lane. Project delayed due to lack of funds. |
TBD |
TBD |
| Kannapolis Dam Repairs and Improvements |
Repairs and upgrades to the concrete chute of the Kannapolis Lake |
2025 |
2026-2027 |
| Rogers Lake Road Bridge Utility Relocations |
Relocation of utilities for the future NCDOT elevated grade crossing at Rogers Lake Road. City portion is complete. NCDOT continues contruction. |
2020 |
2022 |
| Downtown Sewer Main Improvements |
Upgrade to the sewer main within the Irish Buffalo Creek basin. |
2020 |
2026 |
| |
|
|
|
WAYFINDING
|
| |
1st Phase completed. It includes approximately 50 signs throughout the City which will provide direction to the City's major attractions & facilities.
2nd Phase Gateway monuments at the I-85 exits as part of the NCDOT widening project.
|
Spring 2017
2026
|
2022
2026
|
| |
|
|
|